Golden Gate Heights Park

Completed and Opened to the Public July 20, 2021!

Background The renovation of the children’s playground at Golden Gate Heights Park was part of the Let’sPlaySF! Initiative, a partnership between the Recreation and Park Department and the San Francisco Parks Alliance that seeks to inspire creativity and play throughout the City. In total thirteen playgrounds are being prioritized for improvement by a citizen task force to be re-imagined and redesigned for this and future generations of San Francisco’s children.

Scope of Work The renovation of the children’s playground was paired with improvements to the upper lawn and entrance area. These improvements were realized through the Community Opportunity Fund Program from the 2012 Clean and Safe Neighborhood Parks Bond.

Funding

The construction contract award for this project was approved by Recreation and Parks Commission on June 18, 2020 ( PDF ). This construction contract award obtained and complies with all city, state, and federal regulatory approvals, including any that are specific to this project’s funding sources.

Get Out and Play!

Thanks for supporting park improvements in your San Francisco parks! To stay informed and involved, we encourage you to subscribe to Rec and Park eNews .

You can also explore Rec and Park volunteer opportunities – We have park needs in every corner of the city and volunteer opportunities that are as diverse as your interests, skills, and abilities. Have fun in your parks, and get out and play!

Project Updates

Capital Project Update Opens in new window

Golden Gate Heights Playground Update 8/20!

We have wrapped up work on the Golden Gate Heights Playground & Field Renovation. . . Read on…

Capital Project Update Opens in new window

Golden Gate Heights Playground Final Construction Update 7/16!

Hi everyone! We are thrilled to share that construction is wrapping up at Golden Gate Heights and we are opening on July 20th at 11:30. . . Read on…

Capital Project Update Opens in new window

Golden Gate Heights Playground is Opening 7/20!

Hi everyone- We are thrilled to announce the opening celebration of the Golden Gate Heights Playground and Renovation Project! Read on…

Capital Project Update Opens in new window

Golden Gate Heights Playground Construction Update 6/21!

Hi all, We are nearing completion of construction at Golden Gate Heights. . . Read on…

Capital Project Update Opens in new window

Golden Gate Heights Playground Construction Update 5/21!

Hi everyone, The contractor has installed the sod and they are working on the remainder of the landscaping and site furnishings. . . Read on…

Capital Project Update Opens in new window

Golden Gate Heights Playground Construction Update 4/20!

Hi folks- The contractor is working on flatwork around the playground including pouring concrete and asphalt for the paths and picnic area. Read on…

Capital Project Update Opens in new window

Golden Gate Heights Playground Construction Update 3/16!

Hi folks- The playground equipment is installed and the contractor is working on grading the . . . Read on…

Capital Project Update Opens in new window

Golden Gate Heights Playground Construction Update 2/23!

Hi everyone! The playground equipment is being installed at Golden Gate Heights! Read on…

Capital Project Update Opens in new window

Golden Gate Heights Playground Project Update 1/22/21

Hi everyone! Construction is continuing at Golden Gate Heights. Read on…

Capital Project Update

Golden Gate Heights Update Dec ‘20

The contractor will be working on the retaining wall on the north side of the playground Read on…

Capital Project Update Opens in new window

Golden Gate Heights Playground Construction Update 10/29!

Hi everyone- The construction fences are going up at Golden Gate Heights. . . Read on…

Capital Project Update

Golden Gate Heights Playground Construction Has Begun!

Hi folks- Construction has officially begun on the project! Read on…

Capital Project Update

Golden Gate Heights Construction Starting Soon!

Hi everyone- We are getting close to the official start of construction! Read on…

Capital Project Update

Golden Gate Heights Playground Project - Construction Starting Soon!

The contracts are getting signed and we are looking forward to starting construction very soon! Read on…

Capital Project Update

Golden Gate Heights Project is about to start Construction!

We have great news to share! Yesterday, the San Francisco Recreation and Park Commission approved the construction contract award for the Golden Gate Heights Playground and Field Renovation Project! Read on…

Capital Project Update

Golden Gate Heights Playground Project Update 5/22!

We are moving forward with awarding the construction contract on the project next month! Read on…

Capital Project Update

Golden Gate Heights Playground Project Update April 17

Read on…

Capital Project Update

Golden Gate Heights Playground Project Update March 26

We have an exciting update on the Golden Gate Heights Playground & Renovation Project. Read on…

Capital Project Update

GOLDEN GATE HEIGHTS PROJECT OUT TO BID FEB 2020

The project is currently out to bid, which means that potential contractors are reviewing the construction documents and pricing the work Read on…

Capital Project Update

GOLDEN GATE HEIGHTS PROJECT UPDATE FEB 2020

We have exciting news to share! We have completed the design phase of the project Read on…